Governance and Policy - Governance Management - MERC Commission Resolutions - 03-34: For the purpose of approving Change Order #5 to contract #922771 with Hoffman Construction Company of Oregon to reduce the guaranteed maximum price (GMP) specified in the contract by $1,500,000, and authorizing the General... <FULL TITLE IN NOTES>

03-34

<import_note> The imported title was longer than allowed. Full title from import source: 03-34: For the purpose of approving Change Order #5 to contract #922771 with Hoffman Construction Company of Oregon to reduce the guaranteed maximum price (GMP) specified in the contract by $1,500,000, and authorizing the General Manager to execute Change Order on behalf of the Commission </import_note> This record is available in both hard copy and electronic format.